Prince2 Re-Registration: Managing Project Performance

Identify the Missing Words in Project Performance Management

Question

Identify the missing words in the following sentence: The six aspects of project performance to be managed are [?] costs, timescales and scope,

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

The sentence states that there are six aspects of project performance that need to be managed. The three aspects that have been mentioned are costs, timescales, and scope.

Option A includes benefits, progress, and risk. While benefits and risk may be important aspects to manage, progress is not as relevant to project performance management as the other options.

Option B includes benefits, quality, and risk. Quality is a crucial aspect of project management, and managing risks is also important. However, benefits are not necessarily an aspect of project performance that needs to be managed.

Option C includes change, quality, and progress. Change is an important aspect of project management, but it is not one of the six aspects that are mentioned in the sentence. Quality and progress are relevant, but the third option is still missing.

Option D includes benefits, customers, and quality. While quality is important, customers and benefits are not necessarily aspects of project performance that need to be managed.

Therefore, the most appropriate option that completes the sentence is A, which includes benefits, progress, and risk.