Neil works as a project manager for SoftTech Inc.
He is working with Tom, the COO of his company, on several risks within the project.
Tom understands that through qualitative analysis Neil has identified many risks in the project.
Tom's concern, however, is that the priority list of these risk events are sorted in "high- risk," "moderate-risk," and "low-risk" as conditions apply within the project.
Tom wants to know that is there any other objective on which Neil can make the priority list for project risks.
What will be Neil's reply to Tom?
Click on the arrows to vote for the correct answer
A. B. C. D.D.
As a project manager, Neil has identified several risks in the project through qualitative analysis. Tom, the COO of the company, is concerned about the priority list of these risks, which is sorted in "high-risk," "moderate-risk," and "low-risk" categories. Tom wants to know if there are any other objective criteria that Neil can use to prioritize the risks.
In response to Tom's query, Neil can suggest several other criteria to prioritize the risks:
A. Risk may be listed by the responses in the near-term: This means that Neil can prioritize the risks based on the immediacy of the response required to mitigate the risk. Risks that require an urgent response to mitigate can be given higher priority than risks that can be addressed in the long term.
B. Risks may be listed by categories: Neil can categorize the risks based on their nature, such as technical risks, financial risks, legal risks, etc. This can help the project team to focus on specific areas of concern and allocate appropriate resources and expertise to address the risks.
C. Risks may be listed by additional analysis and response: Neil can perform additional analysis to identify the root causes of the risks and develop a comprehensive response plan to mitigate the risks. This can help to prioritize the risks based on the severity of their impact on the project and the likelihood of their occurrence.
D. Risks may be listed by priority separately for schedule, cost, and performance: Neil can prioritize the risks based on their impact on the project schedule, cost, and performance. Risks that have a significant impact on the project schedule, cost, or performance can be given higher priority than risks that have a lesser impact.
In summary, Neil can suggest several objective criteria to prioritize project risks based on their immediacy, nature, severity, and impact on project schedule, cost, or performance. These criteria can help the project team to develop a comprehensive risk management plan that addresses the most critical risks first and allocates appropriate resources and expertise to mitigate the risks.