You have an Azure Stack Hub Integrated System.
You run an add scale unit node operation and it is currently in the progress.
Which of the following operation you should not attempt during the progress of the operation?
Click on the arrows to vote for the correct answer
A. B. C. D. E.Correct Answer: E
The following operations should not be attempted while an add scale unit node operation is already in the progress: Update Azure Stack Hub.
Stop Azure Stack Hub.
Rotate certificates.
Repair scale unit node.
Add another node (the previous add-node action failure is also considered in progress)
Option A is incorrect.
All of the given operations, not only update Azure Stack Hub, should not be performed when the add scale unit node operation is already in progress.
Option B is incorrect.
All of the given operations, not only stop Azure Stack Hub, should not be performed when the add scale unit node operation is already in progress.
Option C is incorrect.
All of the given operations, not only Rotate Certificate, should not be performed when the add scale unit node operation is already in progress.
Option D is incorrect.
All of the given operations, not only Repair Scale Unit Node, should not be performed when the add scale unit node operation is already in progress.
Option E is correct.
All of the given operations should not be performed when the add scale unit node operation is already in progress.
To know more about how to Add scale unit nodes in Azure Stack Hub, please visit the below-given link:
When performing an "add scale unit node" operation on an Azure Stack Hub Integrated System, it is important to avoid certain operations while the operation is in progress. These include:
B. Stop Azure Stack Hub: Stopping the Azure Stack Hub during an add scale unit node operation can cause the operation to fail and result in potential data loss. It is important to allow the add scale unit node operation to complete successfully before attempting to stop the Azure Stack Hub.
E. All the above: Updating Azure Stack Hub, rotating certificates, and repairing scale unit node should not be attempted during an add scale unit node operation. These operations can interfere with the add scale unit node operation and cause it to fail, resulting in potential data loss.
It is important to carefully plan and schedule these operations to ensure that they do not interfere with each other and that they are performed in a safe and timely manner. This will help to ensure the availability, reliability, and security of your Azure Stack Hub Integrated System.