Gold Mine Investment: Calculating Internal Rate of Return (IRR) | Test Prep

Internal Rate of Return (IRR) Calculation for Gold Mine Investment

Prev Question Next Question

Question

Your company is planning to open a new gold mine which will cost $3 million to build, with the expenditure occurring at the end of the year. The mine will bring year-end after-tax cash inflows of $2 million at the end of the two succeeding years, and then it will cost $0.5 million to close down the mine at the end of the third year of operation. What is this project's IRR?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D. E.

A

Time line:

-3,000,0002,000,0002,000,000-500,000

Financial calculator solution: (In millions)

Inputs: CF(0) = -3; CF(1) = 2; N(j) = 2; CF(2) = -.5.

Output: IRR% = 12.699%.

To calculate the internal rate of return (IRR) for the project, we need to determine the discount rate that makes the net present value (NPV) of the cash flows equal to zero. The IRR represents the rate of return at which the project's NPV is zero.

Let's break down the cash flows for this project:

Year 0: Initial investment of $3 million (outflow) Year 1: After-tax cash inflow of $2 million (inflow) Year 2: After-tax cash inflow of $2 million (inflow) Year 3: After-tax cash inflow of -$0.5 million (outflow)

To calculate the NPV, we discount each cash flow to present value using a discount rate and sum them up. The NPV formula is as follows:

NPV = CF₀ / (1+r)⁰ + CF₁ / (1+r)¹ + CF₂ / (1+r)² + CF₃ / (1+r)³

Where: CF₀, CF₁, CF₂, CF₃ = Cash flows in respective years r = Discount rate

We will use the trial and error method to find the discount rate that makes the NPV zero.

Assuming a discount rate of 10%, the calculations are as follows:

NPV = -3 / (1+0.10)⁰ + 2 / (1+0.10)¹ + 2 / (1+0.10)² - 0.5 / (1+0.10)³ = -3 / 1 + 2 / 1.1 + 2 / 1.21 - 0.5 / 1.331 = -3 + 1.818 + 1.653 - 0.376 = 0.095

The NPV is positive, indicating that the discount rate of 10% is too low. Let's try a higher discount rate.

Assuming a discount rate of 15%, the calculations are as follows:

NPV = -3 / (1+0.15)⁰ + 2 / (1+0.15)¹ + 2 / (1+0.15)² - 0.5 / (1+0.15)³ = -3 / 1 + 2 / 1.15 + 2 / 1.3225 - 0.5 / 1.52087 = -3 + 1.739 + 1.513 - 0.328 = -0.076

The NPV is negative, indicating that the discount rate of 15% is too high. We continue this trial and error process until we find the discount rate that results in an NPV closest to zero.

By repeating this process, we find that the IRR is approximately 14.36%. Therefore, the correct answer is B. 14.36%.