If the required rate of return on these projects is 10 percent, which would be chosen and why?
Click on the arrows to vote for the correct answer
A. B. C. D. E.C
NPV(A) = $15,625(PVIFA(10%,5)) - $50,000 = $15,625(3.7908) - $50,000 = $59,231.25 - $50,000 = $9,231.25.
NPVB = $99,500(PVIF(10%,5)) - $50,000 = $99,500(0.6209) - $50,000 = $61,779.55 - $50,000 = $11,779.55.
NPV(B) > NPV(A); $11,779.55 > $9,231.25; Choose Project B.