Consider the following two projects:
Project A -
Initial cash outflow:$1,000,000 -
Cash inflows as follows -
t1: $500,000
t2: $450,000
t3: $250,000
t4: $150,000
t5: $150,000
Project B -
Initial cash outflow: $1,000,000
Cash inflows as follows -
t1: $150,000
t2: $150,000
t3: $250,000
t4: $450,000
t5: $500,000
Assuming a cost of capital of 9%, no taxes, and a $0.00 salvage value for each project at the end of year 5, what is the NPV of each project? Additionally, which of the two projects has the steeper NPV profile?
Click on the arrows to vote for the correct answer
A. B. C. D. E.D
Due to the fact that project B has the majority of its cash inflows coming in later periods, it is more sensitive to changes in the cost of capital than is project A, which has the majority of its cash flows coming in earlier periods. This is exemplified by a steeper NPV profile.