Which of the following statements is correct?
Click on the arrows to vote for the correct answer
A. B. C. D. E.Explanation
A project's stand-alone risk depends on (1) the sensitivity of NPV to changes in key variables and (2) the range of likely values of these variables as reflected in their probability distribution. Sensitivity analysis considers only the first factor.