switch? show interface fcl/5
fcl/5 is down (NPV upstream port not available)

Hardware is Fibre Channel, SFP is short wave laser w/o OFC (SN)
Port WWN is 20:47:00:0d:ac:a4:3b:83

Admin port mode is F, turnk mode is off
snmp link state traps are enabled
Port vsan is 100

Receive data field Size is 2112

Refer to the exhibit.

Interface fc1/5 is offline.

Which action should be taken to troubleshoot the issue?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.