Question 140 of 250 from exam 400-201: Cisco CCIE Service Provider Written Exam

Question 140 of 250 from exam 400-201: Cisco CCIE Service Provider Written Exam

Question

DRAG DROP - The traffic level on a 10 GigabitEthernet core link has passed the threshold of capacity management and needs to be upgraded to a 2x10 GigabitEthernet LAG bundle.

A new 10 GigabitEthernet link is being added, and the new link has been tested free of errors.

The upgrade should be executed in a change maintenance window with minimum impact.

Drag and drop each step from the left onto the proper order for the upgrade migration on the right.

Select and Place:

remove traffic over the 10GigabitEthemet
link changing the IGP metric to the
highest cost

step 1

configure the LAG Bundle-Ethernet
interface and assign the new
10GigabitEthernet link as its member

step 2

re-configure the existing 10GigabitEthernet
link and add it to the new LAG bundle

step 3

reconfigure required routing protocols over
the LAG Bundle-Ethernet and verify all

routing protocol adjacencies are working
correctly

step 4

Explanations

configure the LAG Bundle-Ethernet
interface and assign the new
10GigabitEthernet link as its member

reconfigure required routing protocols over
the LAG Bundle-Ethernet and verify all

routing protocol adjacencies are working
correctly

remove traffic over the 10GigabitEthernet
link changing the IGP metric to the
highest cost

re-configure the existing 10GigabitEthernet
link and add it to the new LAG bundle