Which of the following describes how a project is related to a program?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

A.

72

The correct answer is A. A program is a combination of multiple projects.

Explanation:

  • A project is a temporary endeavor that has a defined scope, timeline, and budget to deliver a unique product, service, or result.
  • A program, on the other hand, is a group of related projects managed in a coordinated way to achieve strategic objectives and benefits that may not be realized by managing each project individually.
  • Programs typically have a longer timeframe, involve more resources, and are more complex than individual projects.
  • Programs are usually made up of multiple projects that are related in some way, such as by a common goal, a shared set of stakeholders, or a similar timeline.
  • By managing related projects as a program, organizations can achieve greater efficiency, reduce duplication of effort, and ensure that all projects are aligned with the overall strategic objectives of the organization.
  • Therefore, option A is the correct answer as it describes how a program is related to a project as a combination of multiple projects.