Question

A contractor is setting up and configuring conference rooms for a convention.

The contractor sets up each room in the conference center to allow wired Internet access going to individual tables.

The contractor measured the distance between the hotel's patch panel to the jack, and the distance is within Cat 5e specifications.

The contractor is concerned that the room will be out of specification if cables are run in each room from the wall jacks.

Which of the following actions should the contractor take to ensure the cable runs meet specifications and the network functions properly?

A.

Place a switch at the hotel's patch panel for connecting each room's cables B.

Place a switch on each table to ensure strong connectivity C.

Place repeaters between the patch panel and the rooms D.

place a switch at the wall jack and run the cables in the room from there.

A.

Explanations

A contractor is setting up and configuring conference rooms for a convention.

The contractor sets up each room in the conference center to allow wired Internet access going to individual tables.

The contractor measured the distance between the hotel's patch panel to the jack, and the distance is within Cat 5e specifications.

The contractor is concerned that the room will be out of specification if cables are run in each room from the wall jacks.

Which of the following actions should the contractor take to ensure the cable runs meet specifications and the network functions properly?

A.

Place a switch at the hotel's patch panel for connecting each room's cables

B.

Place a switch on each table to ensure strong connectivity

C.

Place repeaters between the patch panel and the rooms

D.

place a switch at the wall jack and run the cables in the room from there.

A.

The correct answer is A. Place a switch at the hotel's patch panel for connecting each room's cables.

Explanation: In this scenario, the contractor needs to ensure that the cable runs meet specifications and the network functions properly. The contractor has already measured the distance between the hotel's patch panel and the jack, and the distance is within Cat 5e specifications.

If the contractor runs cables from the wall jacks in each room, there is a risk that the cable runs may exceed the Cat 5e specifications, resulting in poor network performance. Therefore, the contractor needs to take a different approach.

By placing a switch at the hotel's patch panel, the contractor can connect each room's cables to the switch, ensuring that the cable runs do not exceed the Cat 5e specifications. The switch will act as a central point for the cables, allowing for easy management and troubleshooting of the network.

Placing a switch on each table, as suggested in option B, is not an efficient solution as it would require a large number of switches and may result in network congestion and poor performance.

Option C, placing repeaters between the patch panel and the rooms, is also not an ideal solution as it may introduce latency and signal degradation, resulting in poor network performance.

Option D, placing a switch at the wall jack and running cables in the room from there, is not a good option as it does not address the concern of exceeding the Cat 5e specifications and may result in poor network performance.

Therefore, the best option is to place a switch at the hotel's patch panel for connecting each room's cables, as it will ensure that the cable runs meet specifications and the network functions properly.