Question

Which of the following are the BEST risk analysis tools to determine a project's risk level? (Choose two.)

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D. E. F.

CE.

The best risk analysis tools to determine a project's risk level are Monte Carlo analysis and expert judgment.

Monte Carlo analysis is a statistical simulation technique used to assess the impact of different risks on project outcomes. It uses probability distributions to model the range of possible outcomes and then generates random samples to estimate the likelihood of each outcome. Monte Carlo analysis can be used to model a wide range of project risks, including cost, schedule, and technical risks.

Expert judgment is another valuable tool for assessing project risks. It involves seeking input from subject matter experts who have experience with similar projects or expertise in the relevant areas. Experts can provide valuable insights into the likelihood and impact of different risks, as well as strategies for mitigating those risks.

While the other tools listed can be helpful in understanding project risks, they are not as effective as Monte Carlo analysis or expert judgment for determining a project's risk level.

Fishbone diagrams and process flowcharts are useful for identifying potential causes of problems, but they do not provide a quantitative assessment of the likelihood or impact of those problems.

RACI matrices are helpful for clarifying roles and responsibilities on a project, but they do not provide insight into project risks.

Project dashboards can provide a high-level view of project status, but they do not provide detailed risk analysis.

In summary, the two best risk analysis tools to determine a project's risk level are Monte Carlo analysis and expert judgment.