A project manager is not required to participate in performance appraisal meetings with team members.
The project manager is working within which of the following organizational structures?
Click on the arrows to vote for the correct answer
A. B. C. D.D.
The correct answer is likely to be C. Functional.
In a functional organizational structure, team members report to a functional manager who is responsible for their day-to-day work, and the project manager may not have direct authority over team members. Performance appraisals are typically conducted by the functional manager, not the project manager, so the project manager would not be required to participate in those meetings.
Let's briefly review the other options:
Therefore, based on the information provided, C. Functional is the most likely answer.