Daily Project Health Reporting for the Chief Information Officer (CIO)

Best Way to Provide High-Level Project Health Updates

Question

A PM is asked to keep the Chief Information Officer (CIO) informed of a project's health at a high level on a daily basis.

Which of the following is the BEST way for the PM to provide this information?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.

The BEST way for a project manager (PM) to keep the Chief Information Officer (CIO) informed of a project's health at a high level on a daily basis is by providing a dashboard (Option C).

A dashboard is a visual representation of a project's key performance indicators (KPIs) and is an effective tool for high-level communication. Dashboards can provide an instant snapshot of a project's status, enabling stakeholders to quickly understand the project's overall health.

A status report (Option A) is a written document that provides an overview of a project's progress, risks, and issues. While a status report can be useful, it may not be the most effective way to provide high-level information on a daily basis, as it can be time-consuming to create and read.

Meeting minutes (Option B) are a written record of what was discussed in a meeting. While meeting minutes can be useful for tracking discussions and decisions made during a meeting, they may not be the most effective way to provide high-level information on a daily basis, as they can be lengthy and require time to read.

Email (Option D) is a communication tool that is commonly used in project management. While email can be useful for communicating project updates, it may not be the best way to provide high-level information on a daily basis, as it can be time-consuming to read and respond to emails.

In summary, a dashboard is the BEST way for a PM to provide high-level information on a project's health to the CIO on a daily basis, as it provides a visual representation of the project's KPIs and enables stakeholders to quickly understand the overall status of the project.