A project manager is determining a project's critical path to report the projected completion date to stakeholders.
Which of the following information will be required? (Choose two.)
Click on the arrows to vote for the correct answer
A. B. C. D. E. F.BD.
To determine a project's critical path, a project manager needs to gather information about the tasks that must be completed, the order in which they must be completed, and the time required to complete each task. The critical path represents the longest sequence of tasks that must be completed on time in order for the project to be completed on schedule. The following two pieces of information are required to calculate a project's critical path:
Dependencies: The dependencies between tasks refer to the order in which they must be completed. Some tasks may be dependent on others, meaning they cannot begin until a preceding task is completed. A project manager must identify these dependencies in order to determine the critical path.
Durations: The duration of each task refers to the amount of time it will take to complete it. By estimating the duration of each task, a project manager can determine the total time required to complete the project. This information is necessary to calculate the critical path, as it allows the project manager to identify the longest sequence of tasks that must be completed on time to meet the project's deadline.
The other options listed in the question are not required to calculate a project's critical path. While costs may be important for budgeting purposes, they are not necessary to identify the critical path. Schedules and milestones are related to the timing and completion of tasks, but they are not as critical as dependencies and durations when it comes to calculating the critical path. Similarly, holidays are not directly relevant to identifying the critical path, although they may impact the project's schedule.