A project manager is creating the monthly report for top management.
The project manager has collected the information below: AC = 100 - PV = 80 - EV = 120 - Based on this information, the CPI reflects which of the following about the project?
Click on the arrows to vote for the correct answer
A. B. C. D.A.
Explanation - The cost performance index (CPI) is calculated this way: CPI = EV / AC Excerpt From: Kim Heldman.
CompTIA Project+ Study Guide.
iBooks.
To understand the answer, we need to know what each of the given values represents in the Earned Value Management (EVM) formula:
Now, let's calculate the two important EVM metrics using the given values:
Now, let's analyze the answer options:
A. It is under budget. The CPI is greater than 1, which means that the project team is completing the work at a lower cost than planned. So, option A is a possible answer.
B. It is over budget. The CPI is greater than 1, which means that the project team is completing the work at a lower cost than planned. So, option B is not the correct answer.
C. It is ahead of schedule. The SPI is greater than 1, which means that the project team is completing the work faster than planned. However, the question is asking about the CPI, not the SPI. So, option C is not the correct answer.
D. It is behind schedule. There is no information given about the project's schedule, so we cannot determine whether it is behind schedule or not based on the given values. So, option D is not the correct answer.
Therefore, the correct answer is A. It is under budget. The Cost Performance Index (CPI) of 1.2 indicates that the project team is completing the work at a lower cost than planned.