Question

A project encountered a problem and reached a milestone.

In which of the following documents will the stakeholders MOST likely find information on these events?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

Stakeholders are individuals or organizations that have an interest in the project or will be impacted by its outcomes. In a project, it is important to keep stakeholders informed about the progress, issues, and changes that occur during the project's lifecycle.

In this scenario, the project encountered a problem and reached a milestone. The stakeholders would most likely find information on these events in the project's status report.

A status report provides an overall view of the project's progress and status, including the status of milestones, timelines, budget, risks, and issues. It is usually a regular report that is shared with stakeholders, project sponsors, and other interested parties.

The status report is a critical communication tool that helps stakeholders understand how the project is progressing, and what changes or issues are impacting the project. It provides stakeholders with a snapshot of the project's current state and can also help identify potential risks and issues before they become major problems.

An issues log is a document that captures details of the problems encountered during the project and their resolution status. A change log is a document that captures details of any changes made to the project scope, schedule, or budget. Meeting minutes are notes taken during project meetings, which may include details on project progress, decisions, and action items.

While all these documents are important, the status report is the most likely document where stakeholders will find information on the project's progress and significant events such as milestones and problems encountered.