Project Schedule Resource Allocation | CompTIA Project+ Exam PK0-004

Resource Allocation in Project Schedules

Question

A project schedule lists a resource as 50% because it likely:

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

A.

When a project schedule lists a resource as 50%, it means that the resource is assigned to work on the project for only half of the available time. This is likely to indicate option A: the resource is a shared resource.

Shared resources are those that are not dedicated solely to one project or team, but are instead shared across multiple projects or teams. In such cases, the resource may be assigned to work on one project for a certain amount of time, and then move on to work on another project for the remaining time.

Assigning a resource as 50% on a project schedule can help to ensure that the resource's time is divided appropriately between the different projects or teams it is supporting. This can also help to avoid overallocation of the resource, which is when the resource is assigned more work than it can realistically complete in the available time.

Option B is incorrect because a resource shortage would result in a resource being assigned less time than 50%, rather than exactly 50%. Option C is incorrect because 50% allocation does not necessarily indicate overallocation, but rather an appropriate allocation for a shared resource. Option D is incorrect because if a resource was underallocated, it would be assigned less than 50% of the available time.

Therefore, the correct answer is A.