CompTIA Project+ Exam PK0-004: Characteristics of Projects

What Classifies a Project?

Question

A manufacturer is developing a product that will start in one week.

The product has a delivery deadline of 90 days.

Which of the following characteristics classifies this as a project?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

The correct answer is D. Temporary.

Explanation: A project is a temporary endeavor with a specific goal or objective to be achieved. Projects are unique in nature, and they have a defined beginning and end date. In this case, the development of the product is a temporary endeavor as it has a specific deadline of 90 days. Once the product is delivered, the project will come to an end.

Option A, Repetitive, refers to work that is performed in a routine or cyclical manner. It involves repeating the same process over and over again, such as manufacturing the same product multiple times. This is not the case in this scenario as the product is being developed for the first time.

Option B, Ongoing, refers to work that is continuous and does not have a defined end date. This is not applicable in this scenario as the project has a specific end date of 90 days.

Option C, Iterative, refers to a process of repeating and refining a series of steps until a desired outcome is achieved. While this may be a part of the development process for the product, it does not define the project as a whole.

Therefore, the correct answer is D. Temporary.