CompTIA Project+: Answering the Question about Referenced Documents

Referenced Documents

Question

An outsourced project team member approaches the project manager and complains that the contract does not permit overtime.

The project manager had fast- tracked tasks that require additional hours.

Which of the following documents did the project manager fail to reference?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

The document that the project manager failed to reference is the Statement of Work (SOW).

The SOW is a document that outlines the scope of work for a project, including the tasks to be performed, the timeline for completion, and any deliverables that are expected. It also includes any constraints or limitations that may affect the project, such as budget constraints or scheduling limitations.

In this case, the SOW should have outlined the project schedule, including any potential need for overtime hours. If the SOW indicated that overtime was not permitted, then the project manager should have been aware of this limitation and taken it into account when planning the project timeline.

If the project manager did not reference the SOW when fast-tracking tasks that require additional hours, then they may have violated the terms of the contract by allowing overtime when it was not permitted. This could result in legal or financial consequences for the project team or the organization as a whole.

Therefore, it is important for project managers to carefully review all project documents, including the SOW, to ensure that they are aware of any constraints or limitations that may affect the project. This will help to ensure that the project is completed successfully and in compliance with all contractual obligations.