Creating a Transition Plan

Question

Which of the following project phases would MOST likely include creating a transition plan?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.

The correct answer is A. Closing.

Explanation: A transition plan is a document that outlines the steps required to move from the current state to the future state, once the project is completed. It includes details such as timelines, roles and responsibilities, and resources required for the transition.

Creating a transition plan is typically done towards the end of the project, when the project deliverables have been completed, and the project is ready to be handed over to the stakeholders. The purpose of the transition plan is to ensure that the project's benefits are sustained beyond the completion of the project and that the stakeholders can continue to use the project deliverables effectively.

Therefore, the project phase that would MOST likely include creating a transition plan is the Closing phase. This is because the Closing phase is focused on wrapping up the project, finalizing the project deliverables, and transitioning the deliverables to the stakeholders. The transition plan is a critical component of this transition process and is, therefore, typically created during this phase.

The other answer options are less likely to include creating a transition plan:

  • Initiation: This phase is focused on defining the project scope, identifying stakeholders, and securing funding. It is unlikely that a transition plan would be created during this phase.

  • Planning: This phase is focused on developing a project plan, including a project schedule, budget, and resource plan. While it is possible that some elements of the transition plan may be included in the overall project plan, it is unlikely that a separate transition plan would be created during this phase.

  • Execution: This phase is focused on implementing the project plan and delivering the project deliverables. While the project team may begin to plan for the transition during this phase, it is unlikely that a comprehensive transition plan would be created until later in the project, during the Closing phase.