The project sponsor has cut the resources required for project completion.
The project manager cannot complete the project without additional resources.
Which of the following should the project manager do to obtain the resources?
Click on the arrows to vote for the correct answer
A. B. C. D.A.
Option A is the correct answer.
When a project sponsor cuts the resources required for project completion, it is the responsibility of the project manager to take appropriate action. The project manager needs to analyze the situation and identify the reasons for the additional resources required. This information should be documented in a change request.
A change request is a formal document that outlines the proposed changes to the project scope, schedule, or budget. It also describes the impact of the changes on the project, including any risks or issues that may arise as a result. The project manager should submit this change request to the project sponsor for approval.
If the change request is approved, the project manager can proceed with obtaining the additional resources required to complete the project. The project manager may need to adjust the project schedule or budget to accommodate the changes.
Option B is not a feasible solution as hiring additional resources temporarily may not be a cost-effective solution for the project. Additionally, hiring new resources would take time, and the project may not have sufficient time to complete.
Option C is also not a feasible solution as terminating the project would result in a waste of resources and efforts already invested in the project.
Option D is not recommended as it could lead to overburdening the existing project team members, resulting in a lower quality outcome and burnout. It is also not a sustainable solution as team members may not have the required skills or expertise to complete additional tasks.
Therefore, the best option is to document the reasons for the additional resources in a change request and submit it to the project sponsor for approval.