Project Risk Identification and Analysis

Moving Between Project Phases

Question

The project team is moving from high-level risks to detailed risks.

Which of the following project phases is the project team moving between?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.

The project team is moving from high-level risks to detailed risks. This implies that the team has already identified and assessed high-level risks during the initial phase of the project and is now moving to the next phase to identify more detailed risks.

Option A: Execution to monitor and control: This option is not correct because the execution phase comes after the planning phase, and it is where the actual work of the project takes place. The monitor and control phase comes after the execution phase, where the team monitors the progress of the project and makes necessary adjustments.

Option B: Initiation to planning: This option is not correct because the initiation phase is the first phase of the project, where the project is defined and approved, and the high-level risks are identified. The planning phase comes after the initiation phase, where the team develops a detailed project plan.

Option C: Initiation to monitor and control: This option is also not correct because the initiation phase is too early to identify risks in detail, and the monitor and control phase comes after the execution phase.

Option D: Planning to execution: This option is the most appropriate because the planning phase is where the team develops a detailed project plan, which includes identifying risks in detail. Once the plan is developed, the team moves to the execution phase, where the work of the project takes place.

Therefore, the correct answer is D. Planning to execution.