CompTIA Project+ Exam PK0-004: Baseline Schedule Version Number Update

Appropriate Version Number for Second Minor Modification

Question

A minor change to the baseline schedule is required.

This change will be the second minor modification to the schedule.

Which of the following is the appropriate version number?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

The version number for a baseline schedule is used to identify the version or iteration of the baseline, and it typically follows a specific format. In this case, the baseline schedule has undergone two minor modifications, and we need to determine the appropriate version number.

A minor modification to the baseline schedule typically means a change that does not significantly affect the project's overall timeline, budget, or scope.

The appropriate version number can be determined based on the following format: X.Y where X represents the major version number, and Y represents the minor version number.

In this scenario, since the change required is the second minor modification to the baseline schedule, the appropriate version number would be 1.2.

Option A (0.3) is not appropriate since it suggests that this is only the third version of the baseline, and does not reflect the two previous modifications that have already been made.

Option C (2.0) and D (3.0) are not appropriate since they suggest that this is a major change to the baseline schedule, which is not the case.

Therefore, the correct answer is B (1.2).