Determine Work Packages for WBS | Exam PK0-004: CompTIA Project+

The Best Approach to Determine Work Packages for the WBS

Question

A project manager has been assigned a complex project and does not know all the activities required to complete it.

Which of the following if the BEST approach to determine the work packages for the WBS?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

The best approach for the project manager to determine the work packages for the Work Breakdown Structure (WBS) when facing a complex project and does not know all the activities required to complete it is to use the bottom-up approach.

The bottom-up approach involves breaking down the project into smaller, more manageable pieces, starting with the most detailed and specific tasks and working up to higher-level tasks. This approach requires input from team members and subject matter experts who have the necessary knowledge and experience to identify the tasks required to complete the project.

Brainstorming, analogous, and forward pass are also useful tools and techniques for project management, but they are not the best approaches for determining work packages for the WBS in this scenario.

Brainstorming involves generating ideas and solutions through free-flowing discussion, which can be useful for generating creative ideas, but it may not be the most effective approach for developing a structured WBS.

Analogous estimating is a technique that uses historical data or similar projects to estimate the time or cost required for a project. This technique is useful for developing high-level estimates but may not be the best approach for identifying specific work packages.

The forward pass is a technique used in project scheduling to determine the earliest start and finish times for each task in the project. While this technique is important for developing the project schedule, it does not help in determining the work packages for the WBS.

In summary, the bottom-up approach is the best approach for determining work packages for the WBS when facing a complex project and does not know all the activities required to complete it.