A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement.
To have this change approved, the project manager submits a change request that contains which of the following?
Click on the arrows to vote for the correct answer
A. B. C. D.B.
When a vendor informs the project manager that a key component of the project is no longer available and recommends a higher-cost replacement, the project manager needs to submit a change request to have this change approved.
A change request is a formal proposal for an alteration to the project scope, schedule, or budget. It is important to submit a change request as soon as possible to avoid project delays and to ensure that the project sponsor and stakeholders are informed of the proposed changes.
The change request should include the following information:
Therefore, based on the above explanation, option B is the correct answer: