According to the communication management plan, the project scheduler is required to post weekly status reports on the project's intranet site.
From the stakeholders' point of view, accessing the weekly report is an example of:
Click on the arrows to vote for the correct answer
A. B. C. D.D.
The correct answer is D. the pull method.
In project management, the communication management plan outlines how communication will occur, who will be involved, what information will be communicated, and how it will be shared. The communication plan is created to ensure that stakeholders are informed about the project status and progress throughout the project's lifecycle.
In this scenario, the communication management plan requires the project scheduler to post weekly status reports on the project's intranet site. Stakeholders are expected to access the reports to stay informed about the project's progress. The communication is initiated by the stakeholders, who access the report when they need it. This approach is called the "pull" method because stakeholders "pull" the information they need when they need it.
The pull method is an effective way to share information because stakeholders can access the information they need on demand. It also saves time and resources because stakeholders only access the information they need, rather than receiving unnecessary updates that may not be relevant to them.
In contrast, the "push" method involves the project team sending information to stakeholders on a regular basis, regardless of whether they need it or not. This approach can be overwhelming and may result in stakeholders missing important information.
Therefore, the pull method is an example of how stakeholders access project information based on their personal preferences. The other options, interorganizational preferences and the interactive method, do not apply to this scenario.