A project has activities on the critical path that must be completed before other activities can start.
Task A is dependent on Task C before Task D can be completed.
Task A requires task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?
Click on the arrows to vote for the correct answer
A. B. C. D.D.
The critical path is the sequence of activities that determines the duration of the project. The activities on the critical path must be completed on time, or the project will be delayed.
Let's analyze the tasks in the given scenario:
Based on this information, we can determine the appropriate ordering of the critical path:
Therefore, the appropriate ordering of the critical path is option D: B, C, A, D.