Question

During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.

Which of the following documents would contain these items?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

138

The document that contains high-level objectives and goals for a project during the initiation phase is the Business Case.

A Business Case is a formal document that justifies the need for a project by outlining the business problem or opportunity, identifying the project's goals and objectives, and highlighting the benefits that the project will provide to the organization.

The Business Case typically includes information about the expected return on investment, the cost and resource requirements of the project, and the risks associated with undertaking the project.

In the context of the initiation phase, the Business Case helps to establish a shared understanding of the project's purpose, objectives, and expected outcomes among stakeholders. It also provides a foundation for decision-making and resource allocation during subsequent project phases.

A Requirements Document, on the other hand, outlines the specific needs and expectations of stakeholders regarding the project's deliverables, features, and functionalities. It typically includes detailed specifications, user stories, use cases, and other requirements-related information.

A Project Timeline is a graphical representation of the project's schedule, showing the major milestones, activities, and dependencies. It helps stakeholders understand the project's timeline and progress.

A Task Plan is a detailed document that outlines the tasks, activities, and responsibilities required to complete the project. It typically includes information about task dependencies, deadlines, and resource allocation.

Therefore, none of the other options besides the Business Case would contain high-level objectives and goals for a project during the initiation phase.