A project is taking more effort than anticipated.
Which of the following constraints will MOST likely be affected?
Click on the arrows to vote for the correct answer
A. B. C. D.D.
https://programsuccess.wordpress.com/2011/05/02/scope-time-and-cost-managing-the-triple-constraint/When a project is taking more effort than anticipated, it is likely that one or more of the project constraints will be affected. The four main constraints in a project are scope, time, quality, and cost, also known as the project management triangle.
A. Scope: This refers to the defined boundaries and objectives of the project. If the project is taking more effort than anticipated, it is possible that the scope of the project has expanded, causing more work than initially planned.
B. Time: This refers to the duration of the project and the deadlines that need to be met. If a project is taking more effort than anticipated, it is likely that the project will take longer than expected, which can result in missed deadlines.
C. Quality: This refers to the level of excellence that is expected for the project's deliverables. If a project is taking more effort than anticipated, it is possible that the quality of the deliverables may suffer due to time pressures, resource constraints, or other factors.
D. Cost: This refers to the budget allocated for the project. If a project is taking more effort than anticipated, it is likely that the project's cost will also increase due to additional resources required to complete the work.
Based on the above, it is most likely that the time constraint will be affected if a project is taking more effort than anticipated. The increased effort required will result in more time needed to complete the project, leading to delays and missed deadlines. However, it is also possible that the other constraints (scope, quality, and cost) may also be affected to some extent.