Question 135 of 350 from exam PK0-004: CompTIA Project+

Question 135 of 350 from exam PK0-004: CompTIA Project+

Question

A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope.

The project manager is creating the project schedule.

WBS ID [Task Name Predecessors [Duration
1.0.41 [Assign project team - 5 days
10.2 Develop SOW 3 days
10.3 Kickoff meeting Tor 102 [1a
2.0.4 (Create hardware procurement requirements [1.0.3 10 days
[2.0.2 Receive equipment 2.0.4 12 days
3.0 Develop software 2.0.4 [20 days:
4.0.4 install software on hardware 2.0.2,30 [10 days
5.0 Project closeout 14.0.4 3 days

Which of the following calculations accurately shows the critical path?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.