Question 190 of 350 from exam PK0-004: CompTIA Project+

Question 190 of 350 from exam PK0-004: CompTIA Project+

Question

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client.

The budgeted time is 500 hours, and the projected earned value is $30,000.

Project Completion Total Hours Actual Cost
6 months 420 $25.200
4 months 620 $37,200

Which of the following represents the cost variance for both project completions?

Answers

Explanations