Question 274 of 350 from exam PK0-004: CompTIA Project+

Question 274 of 350 from exam PK0-004: CompTIA Project+

Question

Based on the table below:

Task Duration Sequence
Task A 3 days Task B

Task B 8 days Task D, Task E
Task C 4 days Task F

TaskD 2 days Task F

Task E 3 days Task F

Task F 6 days End

Which of the following is the critical path if Task B has extended to ten days?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.