Question 280 of 350 from exam PK0-004: CompTIA Project+

Question 280 of 350 from exam PK0-004: CompTIA Project+

Question

A project manager has developed the initial schedule for an upcoming project.

ID Task Name Start Finish Duration a7isl6 a 45146 7 Fl pape
1 | Task 1 3/6/2017 3/6/2017 1d

2 | Task2 3/7/2017 3/13/2017 Sd —————shhltltt—

3 | Task3 3/7/2017 3/9/2017 3d - os

4 | Task4 3/10/2017 3/17/2017 6d |

5__| Tasks 3/20/2017 3/21/2017 2d |

Using the attached schedule, which of the following is the critical path?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

A.