Question 288 of 350 from exam PK0-004: CompTIA Project+

Question 288 of 350 from exam PK0-004: CompTIA Project+

Question

A project manager is analyzing the cost variances produced when comparing two different projects completions.

Project completion

Estimated hours

Projected cost

Projected variance

6 months

400

$24,000

-$6,000

4 months

600

$36,000

‘$6,000

Which of the following factors could be causing the increased variance for the four-month projects? (Choose two.)

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D. E.

DE.