Question 301 of 350 from exam PK0-004: CompTIA Project+

Question 301 of 350 from exam PK0-004: CompTIA Project+

Question

Based on the table below:

Activity Duration Sequence

Task A 5 Task B. Task C
Task B 10 Task D

Task C 4 Task F

Task D 2 Task E

Task E 5 Task F

Task F 3 End

Which of the following is the float of Task B?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.