Question 303 of 350 from exam PK0-004: CompTIA Project+

Question 303 of 350 from exam PK0-004: CompTIA Project+

Question

Based on the table below:

Activity Duration (days) Predecessor
Task 1 7 None

Task 2 9 1

Task 3 16 1

Task 4 23 1

Task 5 18 2,3

Task 6 6 3,4

Task 7 4 5,6

Which of the following is the total float for the critical path?