A team member has reported Task 3 will be completed ahead of schedule.

ID Task Name Start Finish Duration
1__| Task1 3/6/2017 3/6/2017 ad
2__| Task2 3/7/2017 3/13/2017 sd
3__| Task3 3/7/2017 3/9/2017 3d
4 | Task4 3/10/2017 3/17/2017 6d
5__| Tasks 3/20/2017 3/21/2017 2d

Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.