During the execution phase of a project, a project task has run longer than anticipated.

ID Task Name Start Finish Duration
67) 8\9 hoffe shh 16| 7 B20 21}2223p4)
1 | Taska 3/6/2017 3/6/2017 4d
2. | Task2 3/7/2017 3/13/2017 sd SSS.
3 | Task3 3/7/2017 3/9/2017 3d La-
4_| Task4 3/10/2017 3/17/2017 6d a
5__| Tasks 3/20/2017 3/21/2017 2d s |

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?