Question 93 of 350 from exam PK0-004: CompTIA Project+

Question 93 of 350 from exam PK0-004: CompTIA Project+

Question

During a project, the project manager discovers there is insufficient time allotted for quality control.

The project manager prepared to submit a revised schedule to the CCB.

ID Task Name Start Finish Duration
67] 8]9 hop halis]16 7 eo 2a}zapapal
1 | Task1 3/6/2017 3/6/2017 1d i
2 | Task2 3/7/2017 3/13/2017 sd TT
3__| Task3 3/7/2017 3/9/2017 3d =
4 | Task 3/10/2017 3/17/2017 6d |
5__| Tasks 3/20/2017 3/21/2017 2d =|

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.