You are the project manager for Bluewell Inc.
You are studying the documentation of project plan.
The documentation states that there are twenty-five stakeholders with the project.
What will be the number of communication channel s for the project?
Click on the arrows to vote for the correct answer
A. B. C. D.D.
Communication channels are paths of communication with stakeholders in a project.
The number of communication channels shows the complexity of a project's communication and can be derived through the formula shown below: Total Number of Communication Channels = n (n-1)/2 where n is the number of stakeholders.
Hence, a project having five stakeholders will have ten communication channels.
Putting the value of the number of stakeholders in the formula will provide the number of communication channels.
Hence, Number of communication channel = (n (n-1)) / 2 = (25 (25-1)) / 2 = (25 x 24) / 2 = 600 / 2 = 300 Incorrect Answers: A, B, C: These are not valid number of communication channels for the given scenario.
The number of communication channels for a project is calculated using the formula: n*(n-1)/2 where "n" is the number of stakeholders.
Therefore, for this project with 25 stakeholders, the calculation would be:
25*(25-1)/2 = 300
So the correct answer is D) 300.