Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
Click on the arrows to vote for the correct answer
A. B. C. D.A.
In the PRINCE2 project management framework, the customer/supplier environment is an important concept. It refers to the relationship between the customer (the person or organization that wants the project to be delivered) and the supplier (the person or organization that will deliver the project). The customer/supplier environment is based on the idea that the customer is ultimately responsible for the success of the project, and the supplier is responsible for delivering the project to meet the customer's requirements.
Out of the given options, A. Specify the desired result is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment.
This means that the customer is responsible for specifying what they want the project to achieve. The customer needs to clearly define the project's objectives, scope, and requirements, and communicate them to the supplier. This includes defining the desired results, quality standards, and performance criteria that the project must meet.
In other words, the customer needs to have a clear idea of what they want the project to achieve, and communicate that idea to the supplier. This is essential to ensure that the project is delivered to meet the customer's expectations.
Option B. Provide the resources and skills to deliver the desired result is a responsibility of the supplier, not the customer. The supplier is responsible for providing the resources and skills required to deliver the project.
Option C. Ensure the technical integrity of a project is a joint responsibility of the customer and the supplier. The customer needs to define the technical requirements, while the supplier needs to ensure that the project is designed, developed, and delivered to meet those requirements.
Option D. Develop a project's products is also a supplier's responsibility. The supplier is responsible for developing the project's products and delivering them to the customer.
To summarize, in the PRINCE2 customer/supplier environment, the customer's primary responsibility is to specify the desired result, while the supplier is responsible for providing the resources and skills required to deliver the project, developing the project's products, and ensuring the technical integrity of the project.