Requirements for User Interaction in the GHT Project | CRISC Exam Preparation

User Interaction Requirements

Prev Question Next Question

Question

You are elected as the project manager of GHT project.

You are in project initialization phase and are busy in defining requirements for your project.

While defining requirements you are describing how users will interact with a system.

Which of the following requirements are you defining here?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

While defining requirements, there is need to define three requirements of the project- Business requirement, Functional requirement, and Technical requirement Functional requirements and use case models describe how users will interact with a system.

Therefore here in this stem you are defining the functional requirement of the project.

Incorrect Answers: A: Technical requirements and design specifications and coding specifications describe how the system will interact, conditions under which the system will operate and the information criteria the system should meet.

B: Business requirement, Functional requirement, and Technical requirement come under project requirement.

In this stem it is particular defining the functional requirement, hence this is not the best answer.

D: Business requirements contain descriptions of what a system should do.

The requirement being defined in this scenario is a Functional requirement.

Functional requirements describe what a system is supposed to do, what features it should have, and how users will interact with it. In this case, the project manager is describing how users will interact with the system, which is a key aspect of functional requirements.

Technical requirements, on the other hand, describe the technical specifications that the system must meet, such as performance, scalability, and security.

Project requirements refer to the specific objectives, deliverables, and timelines that are necessary for the successful completion of the project. These can include project management requirements, such as the need for regular status reports or risk assessments, as well as resource requirements, such as the need for a certain number of team members with specific skills.

Business requirements are high-level statements of the goals, objectives, and strategies of the organization that are driving the project. These can include financial goals, regulatory requirements, or strategic objectives.

Therefore, in this scenario, the project manager is defining functional requirements, which are the requirements that describe how the system will function from the user's perspective.