Question

A customer has requested a new feature be included in the next iterative release.

The customer has agreed to move a previously planned feature to a subsequent release and increase the budget.

Which of the following is the MOST appropriate scheduling action?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

The most appropriate scheduling action in this scenario would be to choose option B: add the new feature and reprioritize the product backlog. Here's why:

Option A, "Analyze the critical path and update the WBS with the new feature," is not the best choice because the critical path is a sequence of tasks that must be completed on time for the project to be completed on time. While adding the new feature may impact the critical path, it is not the most important consideration in this scenario. Instead, the focus should be on how to incorporate the new feature into the project while still meeting the overall goals and objectives.

Option C, "Add the new feature to the next sprint and move the old feature to the following sprint," assumes that the project is being managed using an agile framework like Scrum. While this approach might work in an agile environment, it is not the best choice if the project is being managed using a traditional project management approach.

Option D, "Conduct a retrospective with the team to discuss the change and introduce the feature," is a good idea but it's not a scheduling action. A retrospective is a meeting where the team reflects on their performance and identifies opportunities for improvement. While it's important to involve the team in any changes to the project, this option doesn't address the scheduling aspect of the question.

Option B, "Add the new feature and reprioritize the product backlog," is the most appropriate scheduling action. This approach allows the team to incorporate the new feature into the project plan while still meeting the overall goals and objectives. By reprioritizing the product backlog, the team can determine which features are most important to the customer and ensure that they are completed on time and within budget. This approach is flexible and allows the team to adjust the project plan as needed to meet changing requirements.