Gas prices were included in the cost baseline for a transportation and hauling project.
Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?
Click on the arrows to vote for the correct answer
A. B. C. D.C.
Based on the information provided in the question, the cost baseline for a transportation and hauling project includes gas prices. The estimates used to create the baseline were based on historical data. However, potential issues with cost overruns may still occur, and the project manager should consider the root cause of these issues.
Option A: Requirements: Requirements are the specific features, functions, or capabilities that a project must deliver to meet its objectives. While requirements can impact the cost of a project, they are not a root cause of cost overruns in this scenario.
Option B: Lessons learned: Lessons learned refer to the knowledge gained from past experiences that can be applied to current and future projects. While lessons learned may provide valuable insights into managing project costs, they are not a root cause of cost overruns in this scenario.
Option C: Budget: Budget refers to the amount of money allocated for a project. While budget constraints can impact a project's cost, it is not a root cause of cost overruns in this scenario, as the estimates used to create the baseline were based on historical data.
Option D: Environment: Environment refers to the external factors that can impact a project, such as economic conditions, weather, or market trends. In this scenario, the price of gas is included in the cost baseline, so the environment is a potential root cause of cost overruns. If gas prices increase unexpectedly, the project may incur higher costs than anticipated, leading to cost overruns.
Therefore, the correct answer is D. Environment.