The Identify Risk process determines the risks that affect the project and document their characteristics.
Why should the project team members be involved in the Identify Risk process?
Click on the arrows to vote for the correct answer
A. B. C. D.D.
The project team members should be involved in the risk identification so that they will develop a sense of ownership and responsibility for the risk events and the associated risk responses.
Identify Risks is the process of determining which risks may affect the project.
It also documents risks' characteristics.
The Identify Risks process is part of the Project Risk Management knowledge area.
As new risks may evolve or become known as the project progresses through its life cycle, Identify Risks is an iterative process.
The process should involve the project team so that they can develop and maintain a sense of ownership and responsibility for the risks and associated risk response actions.
Risk Register is the only output of this process.
Incorrect Answers: A, B, C: These are not the valid answers for this question.
The Identify Risk process is a critical step in risk management for any project. Its objective is to identify and document potential risks that may affect the project's objectives, whether they are threats or opportunities. The process involves a systematic approach to identify and analyze risks, document them in a risk register, and prioritize them based on their likelihood and potential impact.
Project team members should be involved in the Identify Risk process for several reasons. Here are some of the main reasons:
A. They are the individuals that will most likely cause and respond to the risk events.
Project team members are the ones who are responsible for executing the project tasks and activities. As a result, they are most likely to encounter risks and contribute to their occurrence. Therefore, their involvement in the Identify Risk process can provide valuable insights into the potential risks and help identify their root causes. Moreover, team members can offer suggestions for potential risk response strategies based on their experience and expertise.
B. They are the individuals that will have the best responses for identified risks events within the project.
Project team members have a wealth of knowledge and expertise related to the project, which is why they are well-equipped to identify and respond to risks. They can provide valuable input in terms of risk mitigation, contingency planning, and risk transfer strategies. Team members can also help evaluate the feasibility and effectiveness of different risk responses based on their experience with similar projects or situations.
C. They are the individuals that are most affected by the risk events.
Risks can have significant impacts on project team members, both in terms of project outcomes and personal wellbeing. For example, a risk event that leads to project delays may result in overtime work or additional stress for team members. As a result, their involvement in the Identify Risk process can ensure that all potential risks are considered, and risk response strategies take into account the team's well-being and safety.
D. They are the individuals that will need a sense of ownership and responsibility for the risk events.
Project team members are responsible for the project's success, and they will play a vital role in implementing risk response strategies. Therefore, their involvement in the Identify Risk process can create a sense of ownership and responsibility for the risks identified. This will increase their motivation and commitment to the project and the risk management process.
In conclusion, involving project team members in the Identify Risk process is essential for effective risk management. It ensures that all potential risks are considered, risk response strategies are feasible and effective, and team members have a sense of ownership and responsibility for the risk events.