Prince2 Re-Registration: Incorporating Estimated Time and Costs in Initiating a Project Process

Incorporating Estimated Time and Costs in Initiating a Project Process

Question

During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

During the Initiating a Project process, the Prince2 project management methodology suggests creating several key documents that help the project team understand the purpose, objectives, scope, and constraints of the project. One of these documents is the Project Plan, which outlines how the project will be executed, monitored, and controlled to achieve its goals.

When creating the Project Plan, the project manager estimates the time and cost required to complete each activity and deliver each product. The purpose of this estimation is to create a baseline against which the actual progress and performance of the project can be measured and controlled.

Therefore, during the Initiating a Project process, the Project Plan is updated to incorporate the estimated time and costs for each activity and product. The Project Plan is a living document that is updated throughout the project's life cycle to reflect changes in scope, schedule, budget, risks, and quality.

The Project Plan is not listed as one of the possible answers in the given question. However, the answer that best reflects the update of the Project Plan is option C, the Project Brief. The Project Brief is a summary document that describes the key aspects of the project, including its objectives, scope, deliverables, and timelines. It provides a high-level overview of the project's purpose and vision, and it serves as a reference point for all stakeholders.

The Project Brief is updated during the Initiating a Project process to incorporate the estimated time and costs from the Project Plan. This ensures that the Project Brief remains aligned with the Project Plan and that all stakeholders are aware of the estimated time and costs required to complete the project successfully.

In summary, during the Initiating a Project process, the Project Plan is updated to incorporate the estimated time and costs for each activity and product. The Project Brief is then updated to reflect the estimated time and costs from the Project Plan, ensuring that all stakeholders are aware of the project's objectives, scope, timelines, and budget.