You are the project manager of the GHE Project.

You have identified the following risks with the characteristics as shown in the following figure:

Risk Probability |Impact
A 60 10,000
B 10 36,000
c 25 75,000
D 40 45,000
E 50 47,000

How much capital should the project set aside for the risk contingency reserve?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.