SIMULATION - You are a functional consultant for Contoso Entertainment System USA (USMF)
The factory of USMF has a shift that runs during the hours of 06:00 to 14:00 from Monday to Friday.
You plan to create a calendar that will use the shift.
You need to create the factory shift in the system.
To complete this task, sign in to Dynamics 365 portal.
See explanation below.
You need to configure a working time template to define the hours 06:00 to 14:00.Then you set up a working time calendar to define the working days.For this question, we just need to configure the working time template.
1
Click Organization administration > Common > Calendars > Working time templates.
Click New to create a new line.
2
On the Overview tab, in the Working time template field, enter an alphanumeric identifier of up to 10 characters.
3
In the Name field, enter a descriptive name for the template.
4
Select the tab that corresponds to the day of the week that you want to define working hours for, and click Add to create a new line.
5
In the From field, enter the starting time for the day or the period.
6
In the To field, enter the ending time for the day or the period.
This can be defined as a day, a shift, or a temporary stop in operation, such as a lunch period.
7
In the Efficiency field, enter the efficiency percentage.
8
In the Property field, select the property for the selected day's working time template.
9
Repeat steps 4 through 8 for each day of the week.
As a functional consultant for Contoso Entertainment System USA (USMF), you need to create a calendar that will use the factory shift. Here are the steps to create the factory shift in the system:
You have now successfully created the factory shift in the system, and it can be used in various manufacturing processes to plan production and resource allocation based on the shift timings.