Two Possible Ways to Achieve Seasonal Production Targets in Microsoft Dynamics 365 Supply Chain Management, Manufacturing

Plan Jobs for Seasonal Production Targets - MB-320 Exam Question Solution

Question

A customer produces light projection toys for holiday decorations throughout the year.

You are in the first month of a season.

Production flows take one day to complete.

The floor supervisor reports that seasonal production targets will not be met.

You review the Kanban schedule board and identify thousands of unplanned jobs.

You need to plan the jobs to be completed two weeks prior to the start of the next season.

What are two possible ways to achieve this goal? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D. E.

BD.

https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/lean-manufacturing-kanban-job-scheduling

The goal is to plan the production jobs to be completed two weeks prior to the start of the next season. The production flows take one day to complete, and there are thousands of unplanned jobs on the Kanban schedule board. There are two possible ways to achieve this goal, as follows:

Option A: Set the Automatic planning option for each unscheduled job to Yes If the Automatic planning option is set to Yes for each unscheduled job, the system will automatically schedule the jobs based on their due date and the available resources. The system will take into account the lead time, capacity, and availability of resources such as machines, labor, and materials. This option will save time and effort in manually scheduling each job, and will ensure that the jobs are completed by their due date. However, it may not be possible to complete all the jobs in the available time frame, especially if there are capacity constraints or material shortages.

Option B: Manually schedule each unscheduled job on its due date If each unscheduled job is manually scheduled on its due date, the production plan will be tailored to the specific requirements of each job. This option will ensure that the jobs are completed on time, and will allow for adjustments to be made in case of unexpected events such as machine breakdowns or material shortages. However, this option may be time-consuming and may require a significant amount of effort to schedule all the jobs individually.

Option C: Set the Automatic planning option for each unscheduled job to No If the Automatic planning option is set to No for each unscheduled job, the jobs will not be automatically scheduled by the system. This option may be useful if the jobs require special attention or if they are part of a larger project that requires manual intervention. However, this option may result in delays or missed due dates if the jobs are not manually scheduled in a timely manner.

Option D: Manually schedule each unscheduled job forward from the date of the end of the season If each unscheduled job is manually scheduled forward from the date of the end of the season, the production plan will be optimized for the available time frame. This option will ensure that the jobs are completed before the start of the next season, and will allow for adjustments to be made in case of unexpected events. However, this option may require a significant amount of effort to schedule all the jobs individually, and may not be feasible if there are capacity constraints or material shortages.

Option E: Manually schedule each unscheduled job to the next period of the start of the next season If each unscheduled job is manually scheduled to the next period of the start of the next season, the production plan will be optimized for the next season. This option will ensure that the jobs are completed in time for the next season, and will allow for adjustments to be made in case of unexpected events. However, this option may require a significant amount of effort to schedule all the jobs individually, and may not be feasible if there are capacity constraints or material shortages.

In summary, the two possible ways to achieve the goal of planning the jobs to be completed two weeks prior to the start of the next season are to either set the Automatic planning option for each unscheduled job to Yes or to manually schedule each unscheduled job on its due date. Option A will save time and effort but may not be feasible if there are capacity constraints or material shortages. Option B will ensure that the jobs are completed on time but may be time-consuming and require a significant amount of effort.